LOBBY RENOVATION FINAL PHASE
- Commences Wednesday November 18, 1998
- The Final Phase is scheduled to last between November 18, 1998-November 20, 1998
- The Final Phase will involve the replacement of the concrete under the front door canopy with brick pavers.
*** IMPORTANT***
On Wednesday, Thursday, and Friday (November 18, 19, 20) the entry/exit process of the Lauren will be altered. The main entrance on 20th Street will be closed. All persons entering the building will enter via the N Street door. You should then access the elevators by going up to the 1st floor. Mail and packages will continue to be picked up at the front desk.
We apologize for the delay in completing this portion of the renovation. Unfortunately bureaucratic red tape precluded adhering to not only the original schedule, but also to several revisions thereof.
Please feel free to contact me if you have any questions in this matter.
Thank you for your Patience and Understanding!
Walter Krolman Property Manager
November 17, 1998