Elevator walls and ceiling work will start March 29
and will end April 2 and flooring work will start April 5 and will end
April 7 according to latest information provided by the contractor.
The schedule is subject to unforeseen circumstances
though an outside completion date of April 23 had been supplied by the
contractor.
One elevator will be out of commission during its
renovation while the other one will be open for normal use. Work will
take place during regular business hours of 9:00AM-5:00PM. Along with
completion of hallway punchlist items which is currently ongoing this
is the final step of renovations to the association's common areas.
|