|
|||||||||
|
Water Turn-Off Date Has Been Confirmed! As initially mentioned
in a memo posted April 2, 2007 Oasis Mechanical will be replacing a number of
domestic water valves throughout the building. In order for this to be
accomplished it will be necessary to turn off ALL water to the building.
Water currently in the pipes will have to be drained. The second of these
water-shut offs will allow us to replace and, if called for, relocate from
residential units to the main hallway those valves servicing residential units
that are located in the ceiling above the 10th floor hallway. Water will be turned off for the entire
building Monday June 11, 2007 8:30
AM-4:30 PM & Tuesday June 12, 2007 8:30 AM-4:30 PM Important things for you
to know: 1. Please
make sure all hot and cold water valves are turned OFF in both your bath(s) and
kitchen. 2. After
the pipes are refilled and you run your faucet you may experience some air
and/or sediment. This is perfectly normal. Please turn your faucets back on
slowly. 3. If
work is completed prior to 4:30 water will be turned back on sooner. The front
desk will be kept apprised of progress. 4. We
hope that with the multitude of crews being supplied by Oasis that these two
days will allow the project to be brought to conclusion. However, there is a
distinct possibility than an additional day of labor (and corresponding water
shut-off) will be required. 5. We
hope to be able to maintain the building wide air conditioning. However, if the
water level in the cooling tower is sufficiently reduced the system will shut
down on a safety mode. 6. Because
all work is being done on the top floor water will only have to be drained down
to that level and thus some lower floors will most likely initially still have
water. However, as the system will not be refilled during the day additional
floors will also most likely lose their water. As
always, many thanks for your cooperation and understanding! Walter J.
Krolman Property
Manager-June 6, 2007 |
|||||||||