June
18, 2002 In
our last official memo dated May 24, 2002 we noted that the railing had arrived
at the contractor’s shop and, after a final scan for hidden elements, should
start to be installed May 30th. Regretfully the railing was shipped with an
improper finish and had to be returned to the manufacturer. The problem was
corrected and the railing has now been received back at the Lauren. Installation of the
railing commenced Monday June 17th. The
pool has been painted and is expected to be filled at the end of this week.
Furniture is tentatively set for delivery also at the end of this week. Based
upon our general contractor’s current schedule we are now estimating (and more
than fairly confident) that the roof and pool will be
usable by Saturday June 29th. Items
such as planters, plantings, woodwork as well as punchlist items for the roof
replacement will installed/performed as expediently as possible though most
likely will continue throughout the summer.
Again,
our thanks for your patience and understanding. We think the end result will be
worth the wait! Sincerely,
Walter
J. Krolman |
|||