TO Residents of The Lauren
FROM Walter Krolman, Property Manager
RE Roof Schedule-Update
DATE 08 February 02
We have been advised that the new roof membrane will be completed tomorrow.
It is anticipated that there will then be a lull in Saturday construction for
several weeks.
The next stage involves the installation of a metal coping around the
entire perimeter of the roof. This coping is screwed into the recently erected
parapet.
The manufacturers quote a six (6) week lead time for the pavers and
railing. Thus these items plus the accompanying insulation and ballast are
projected to be started at the end of March/early April.
|